A U.S. judge said on Feb. 28 he hopes to decide by March 7 regarding a request by Native American tribes for the Army Corps of Engineers to withdraw an easement on religious grounds for the final link of the Dakota Access Pipeline.At a hearing, Judge James Boasberg of the U.S. Court in Washington, D.C., said he hoped to provide a written ruling by that time on the injunction requested by the Standing Rock Sioux and Cheyenne River Sioux tribes regarding the final section of the line that will go under a lake in North Dakota.Boasberg said if Energy Transfer Partners, the company building the $3.8 billion line, expects the project will be completed and oil will flow before March 7, that the company must give him 48 hours’ notice so he can release his ruling.
[Read More …]
Source: Daily Dose of ShaleDirectories.com News
February 28, 2017